  1. TyBOTImage: Advanced Construction Robotics

    D.T. Read Steel tied 37,942 rebar intersections on a 12,343 sq ft bridge deck with TyBOT in five days.

    Rt. 29 over Ward Road, Lynchburg, USA

    TyBOTD.T. Read Steel

  2. TyBOTImage: Advanced Construction Robotics

    D.T. Read Steel used TyBOT to tie rebar on the I-40 Jonathan Creek bridge deck for general contractor Kiewit in April to May 2024; TyBOT completed 58,215 ties over nine shifts.

    I-40 Jonathan Creek, USA

    TyBOTD.T. Read Steel

Deployments

Records where D.T. Read Steel ran the robot on site.

  1. D.T. Read Steel used TyBOT to tie rebar on the I-40 Jonathan Creek bridge deck for general contractor Kiewit in April to May 2024; TyBOT completed 58,215 ties over nine shifts.

    Date
    2024
    Country
    USA
  2. TyBOT tied rebar alongside D.T. Read Steel on the Rt. 29 Ward Road bridge in Lynchburg, Virginia, completing the 12,343 sq ft deck in five days with 37,942 ties, including a record 17,155 ties in one shift on July 13, 2022.

    Date
    2022
    Country
    USA
  3. D.T. Read Steel used TyBOT on 12 spans of the 18-span I-30 Crossing bridge deck in Little Rock, Arkansas, from September 2023 to April 2024, tying 669,142 rebar intersections, 75% of the total.

    Date
    2023
    Country
    USA
  4. D.T. Read Steel used TyBOT on the Intracoastal Waterway bridge in Gulf Shores, Alabama, a 101,653 square foot deck requiring 141,692 ties, for general contractor Scott Bridge Company; the job finished on November 4, 2025.

    Date
    2025
    Country
    USA
  5. D.T. Read Steel used TyBOT on the NASA Causeway Bridge Replacement in Titusville, Florida, where it completed 139,261 ties across 50% of the top and bottom mats on a significant portion of the deck.

    Date
    2025
    Country
    USA
  6. D.T. Read Steel used TyBOT on the SR 107 bridge over the Nolichucky River in Greenville, Tennessee, a 23,653 square foot deck requiring 50,119 ties, for general contractor Kiewit; the job finished in April 2025.

    Date
    2025
    Country
    USA
  7. D.T. Read Steel used TyBOT on the SR 81 bridge over the Nolichucky River in Jonesborough, Tennessee, a 15,627 square foot deck requiring 18,236 ties, for general contractor Kiewit; the job finished on April 22, 2025.

    Date
    2025
    Country
    USA
  8. D.T. Read Steel used TyBOT on the Business Route 29 bridge over the Staunton River in Campbell County, Virginia, a 55,950 square foot deck requiring 85,644 ties, for general contractor Kiewit Corporation; the job finished in September 2020.

    Date
    2020
    Country
    USA
  9. D.T. Read Steel was using TyBOT on the I-26/I-95 Interchange Improvement Project in Harleyville, South Carolina, and planned to take delivery of two TyBOT units, the first in early December and the second by the end of 2025.

    Country
    USA

Is this D.T. Read Steel?

Claiming this page is free. Confirm the record, add projects, figures and dates, set the regions and jobs you take, and choose whether to receive job requests.

Claim this page

Leave an email and we'll get in touch about maintaining this profile.

How corrections work