  1. LIFTBOT

    Three Bilfinger scaffolders, not eight, built scaffolding around 40 m reactors at the UK's largest refinery with a LIFTBOT hoist.

    UK Petrochemical Refinery (largest), UK

    LIFTBOTBilfinger

  2. Voliro TImage: Voliro AG

    Bilfinger's crew used Voliro T with a UT payload to inspect a 400 ft stack at a customer's facility in Missouri, completing it in 1.5 days with a two-person crew instead of 25 days with scaffolding.

    400 ft stack inspection, USA

    Voliro TBilfinger

  3. Voliro TImage: Voliro AG

    Bilfinger used Voliro T with a UT payload to inspect three columns and associated piping at a client's chemical plant, finishing in 2.75 days with a two-person crew versus about 8 days with rope access.

    Chemical plant columns and piping inspection

    Voliro TBilfinger

Deployments

Records where Bilfinger ran the robot on site.

  1. Bilfinger used a KEWAZO LIFTBOT hoist to assemble scaffolding around 40-meter-high reactors at the UK's largest petrochemical refinery, an 8-week project worked by three scaffolders instead of at least eight.

    Date
    2021
    Country
    UK

Is this Bilfinger?

Claiming this page is free. Confirm the record, add projects, figures and dates, set the regions and jobs you take, and choose whether to receive job requests.

Claim this page

Leave an email and we'll get in touch about maintaining this profile.

How corrections work